ENVIRONMENTAL REMEDIATION PROJECTS

Trestle Area Remedial Action Project
Owner: Montana Department of Environmental Quality

Project consisted of :

  • Removal of contaminated soil within the floodplain
  • Haulage of contaminates to the Opportunity Ponds Repository
  • Import of floodplain alluvium, and cover soil
  • Stabilization of approximately 600 lf of Stream Bank
Silver Bow Creek Cleanup Phase 9
Owner: Montana Department of Environmental Quality

Project consisted of :

  • Removal of 429,000 cy of Contaminated Soils along Rivers edge;
  • Regrade 122 acres of floodplain;
  • Load, Haul, and Placement of 91,000 cy of vegetative backfill;
  • Reconstruction of 12,600 feet of stream channel.
Upper Clark Fork Phase 5&6 Remediation Project
Owner: Montana Department of Environmental Quality

Project consisted of :

  • Removal of 532,000 cy of Contaminated Soils along Rivers edge;
  • Import of 405,000 cy of Floodplain material;
  • Placement of 134,000 cy of cover soil;
  • Development of 53 Acres of Wetland;
  • Restoration & Enhancement of 25,000 feet of Stream Bank.